Sugden Sports Hall – Sports Hall Lighting Replacement
Central Electrical & Mechanical was appointed by Armitage Construction and the University of Manchester to renew the lighting within Sugden Sports Hall.
The project involved replacing the existing lighting with a new installation, presenting technical challenges due to the engineering requirements of fitting the lights in the opposite orientation to the original arrangement. Central’s engineers worked through these challenges to achieve the required installation.
Despite unforeseen delays at the commencement of the project, the team was asked by the client to complete the works one week earlier than originally anticipated. By working weekends and adapting the programme, Central Electrical & Mechanical achieved the revised completion date at no additional cost to the client.