Sugden Sports Hall

Sugden Sports Hall – Sports Hall Lighting Replacement

 

Central Electrical & Mechanical was appointed by Armitage Construction and the University of Manchester to renew the lighting within Sugden Sports Hall.

The project involved replacing the existing lighting with a new installation, presenting technical challenges due to the engineering requirements of fitting the lights in the opposite orientation to the original arrangement. Central’s engineers worked through these challenges to achieve the required installation.

Despite unforeseen delays at the commencement of the project, the team was asked by the client to complete the works one week earlier than originally anticipated. By working weekends and adapting the programme, Central Electrical & Mechanical achieved the revised completion date at no additional cost to the client.

How can we help you?

Arrange a call using the form below

    Electrical Works

    • Renewal of the existing lighting installation within Sugden Sports Hall
    • Removal and replacement of the existing sports hall lighting
    • Installation of new lighting in the required alternative orientation
    • Engineering solutions to accommodate the revised lighting arrangement
    • Adaptation of the installation to suit the existing building and structural requirements
    • Coordination of lighting works with the requirements of Armitage Construction and the University of Manchester
    • Management of installation challenges associated with the revised light positioning
    • Weekend working to recover time following unforeseen commencement delays
    • Completion of the project one week ahead of the revised anticipated deadline
    • Delivery of the additional working hours at no extra cost to the client

     

    The Sugden Sports Hall project demonstrates Central Electrical & Mechanical’s ability to overcome technical installation challenges while maintaining a demanding programme. Through practical engineering solutions and flexible working, the team completed the lighting renewal ahead of the revised deadline and without additional cost to the client.