Ayrshire Metals – Factory Partial Rewire & Lighting Upgrade
Central Electrical & Mechanical was invited to tender for electrical works at Ayrshire Metals following an unsatisfactory Electrical Installation Condition Report (EICR) carried out by another electrical contractor. The report identified the need for a partial rewire within the factory to address the condition of the existing electrical installation.
During the initial site visit, Central also identified that lighting levels throughout the premises were particularly poor, creating an unsuitable working environment. Rather than simply replacing the necessary lighting circuits, the team recommended carrying out a wider lighting upgrade at the same time, providing a more cost-effective solution for the client.
The combined proposal was accepted, with Central securing the contract below the client’s budget. The project was successfully completed over six weeks.