Raddison Manchester Airport

Radisson Manchester Airport – Conference Room Air Conditioning Electrical Installation

 

Central Electrical & Mechanical was appointed to install the electrical supplies serving the air-conditioning units within the conference rooms at Radisson Manchester Airport.

The project presented additional challenges as the conference centre needed to remain operational throughout the works. To minimise disruption to hotel guests and business meetings, engineers arranged their working hours around room usage, starting early and carrying out alternative works in the basement when conference rooms were occupied.

The team also worked throughout the Christmas break to complete the installation while the conference centre was not in use.

How can we help you?

Arrange a call using the form below

    Electrical Works

    • Installation of electrical supplies to the air-conditioning units serving the conference rooms
    • Electrical connections to support the operation of the air-conditioning equipment
    • Installation of associated cabling and electrical infrastructure
    • Electrical works within the conference room areas
    • Associated electrical works in the basement serving the outdoor air-conditioning units
    • Coordination of electrical installations with the positioning and requirements of the air-conditioning equipment
    • Scheduling works around conference room bookings and hotel operations
    • Early starts and out-of-hours working to minimise disruption
    • Completion of the installation during the Christmas break when the conference centre was not in use

     

    The Radisson Manchester Airport project demonstrates Central Electrical & Mechanical’s ability to deliver specialist electrical works within a busy operational environment. Careful planning and flexible working arrangements allowed the team to complete the installation while minimising disruption to the hotel’s conference facilities.